ICI Steps

Click on the wheel to see the steps of the project cycle

Other Technical Areas
Hydrogen
Energy Finance
Energy Access
Energy Efficiency (EE)
Renewable Energy (RE)

The Finnish government agency prepares brief progress and financial reports to the MFA as a basis for payments. Progress reporting and invoicing takes place twice a year, or as defined in the contract. Progress reports serve as the basis for monitoring of project progress. The report is first sent to the Facilitation Consultant for review and initial approval. The Facilitation Consultant either approves the report, after which it can be sent to the responsible Desk Officer in the Ministry for Foreign Affairs, or requests further information or clarification from the Finnish reporting agency within seven days from receipt. The signed report functions as an invoice in the billing system of the Government

# of reportReporting periodPrepared duringSend to Facilitation Consultant bySend to MFA Desk Officer by
1st yearly report1 Dec – 31 MayMay – June1st/2nd week of Jun (flexibility if requested)June
2nd yearly report1 June – 30 NovNov – Dec1st week of Dec (strict due to end-year)3 weeks before end of the year

More information on each step is available in the ICI Manual and ICI Trainings.